Since the last post we have made a lot of progress. It has not been without its challenges, however here are some pictures to walk you through the progress. The first 6 pictures are all taken from the same relative location. We have also set a date for the straw bale workshop. June 8-9, 2013. Please email StrawBaleAustin@gmail.com for further details if you are interested in coming out and helping us raise our walls. Thanks again for taking a look!
The forms are completed and the fill has been brought in. |
The plumbing almost near completion |
Plumbing is complete! Ready to pour! |
Concrete has been poured! Here some of the workers are smoothing out the concrete after its been poured. |
Here it is after the forms have been removed. You can see the rebar sticking up around the edge in preparation to hold the straw bales in place. |
Here is a picture of the beam that will span our kitchen. |
Garage forms up, pile of fill, one Yasmin and an Oprah... |
Garage plumbing completed, ready for concrete! |
Here is a shot of the back side of the garage |
Right before they poured the concrete |
Framing only took a couple hours |
And here it is the very next day...These guys are quick! |
Im ready for all the piles of junk to get off the property |
Looking good ya'll! Cant wait for the bale raising!!!
ReplyDelete-Sarah